New interior buildout of 2,100 SF within a 60,000 SF warehouse space. The space needed to be turned around quickly for the new tenant. The new office space includes a set of bathrooms, breakroom, offices, and IT room. A large demising wall was installed to divide the 120,000 SF building. The warehouse space will be utilized for storage and populated with racking. There were 16 new charging stations installed for the forklifts utilized to fill the new racking system.


The mechanical, electrical, plumbing, and sprinkler scopes were completed on design/build.


Prime worked closely with the electrician to coordinate and provide the proper light levels in the warehouse area. The overhead doors also required new air-bag dock levelers that were cut into the existing concrete slab and foundation system.

Project Specs:

  • Tenant Improvements - new tenant build out

  • Project Size & Scope: 2,100 SF, new office space, bathrooms, break room, offices, IT room and demising wall

  • Owner: Capp Industries, Inc.

  • Architect: BDH

Prime General Contractors Logo.png
20 year anniversary emblem_prime general_transparent.png

Contact Us

1710 Alexander Road
Eagan MN 55121

Mon- Fri:  8am- 5pm

Join the Prime Community

  • Prime General Contractors on LinkedIn
  • Prime General Contractors on YouTube
  • Google Review for Prime General Contractors

For proposals or any inquiry, contact us

Thanks for submitting!

© 2025-2026 Prime General Contractors LLC. All rights reserved. Images used with permission.

Your privacy is important to us. This is a secure site using encrypted Secure Socket Layer technology.

Your data is safe and will not be shared.

bottom of page